Draft Project Plan - 1

The following outline is a draft plan for the project. After detailed discussion with my supervisor, the final one will be made before 27/03/2014 (Topic proposal due date).


  1. Background research and requirement analysis
    Jan 3rd ~ Mar 27th (Topic Proposal due)
    1. Background related literature review
      Jan 3rd ~ Jan 6th
    2. Requirement analysis
      Jan 6th ~ Mar 7th
      1. mock up
      2. simple prototype
      3. meeting with UI designer and psychology expert
    3. Scope negotiation and feature selection
      Mar 7th ~ Mar 14th (Topic Registration due)
    4. Formal requirement document and project plan
      Mar 14th ~ Mar 21st
  2. Design
    Mar 31st ~ Apr 25th
    1. System structure
    2. Back end
      1. Detailed software structure design
      2. Data model
    3. Front end?
    4. Development iteration plan
    5. Learn Spring
  3. Development
    Apr 28th ~ Jul 20th, except the exam weeks; 1 week per iteration
    1. Development
    2. Progress report
      May 19th ~ Jun 5th (Progress Report due)
      1. draft
        May 19th ~ May 29th
      2. final
        May 30th ~ Jun 5th
  4. Test and draft thesis
    Jul 21st ~ Oct 10th (Draft Thesis may due on Oct 24th)
    1. Alpha test
      Jul 21st ~ Jul 27th
    2. Inner beta test
      Jul 28th ~ Aug 8th
    3. release and field test
      Aug 11th ~ Oct 10th
    4. draft thesis and wait for test result
      Aug 11th ~ Oct 10th
  5. Data analysis
    Oct 11th ~ Oct 17th
  6. Final thesis
    Oct 17th ~ Nov 6th (Final Thesis may due on Nov 7th)
  7. Presentation
    Nov 7th ~ Nov 13th (Presentation may be on Nov 14th)